KW 32

 

Panorama gallery on Pilatus Kulm now taking shape. Next stage is to concrete the roof.

KW 31

 

1 August celebrations successfully held in Queen Victoria Saal.

KW 29

 

Restoration work to Queen Victoria à-la-carte restaurant will shortly be completed.

KW 23 - 28

 

The first guests have already stayed overnight in the new Hotel Pilatus-Kulm

KW 21-22

 

Pilatus Business Centre opened at Whitsun

KW 16

 

Completion work on the Pilatus Business Center going ahead at full speed

KW 15

 

Preparatory work for the panorama gallery begins on the terrace

KW 13

 

The large external area at Alpnachstad is paved ...

KW 13

 

It's all go  ...

KW 10-12

 

The external area at Alpnachstad has noticeably changed

KW 9

 

The show room in Hotel Pilatus Kulm is now finished

KW 8

 

Alpnachstad the new ticket office 

KW 6-7

 

We are progressing well despite poor weather

KW 6-7

 

The foundations for the ticket office have been prepared

KW 4-5

 

Progress is now in evidence

KW 3

 

Progress in evidence

KW 2

Alpnachstad - Here we go!
KW 1

Still 4 ½ months to the first opening
KW 52

Excavation of the guest lift
KW 51

Dust & fog
KW 50

 

Clearing work is going forward 

KW 49

Onset of winter – material transport by helicopter


KW 48

 

Modernization of fat separator and hollowing-out various spaces


KW 46-47

 

Start of construction – here we go!